Steel erection support, from a manual to a full team on site

Most erection problems start before the steel arrives: anchor bolts out of position, no laydown area, a crane too small. This page covers what your site must have ready, what we bring, and how problems are fixed.

Laos

Erected by GGSteel

Myanmar

3 stadiums erected

Indonesia

Site construction

3 levels

Manual, supervisor, full team

Options

Three levels of support

Manual and remote supportSite supervisorsFull erection team
Erection manual, marking plans, bolt listsYesYesYes
Video support from our engineersYesYesYes
Supervisors on site—1–3 peopleIncluded
Erection crew, cranes, toolsYour contractorYour contractorGGSteel
Phù hợp nhất choExperienced local erectorsLocal crew new to this structureRemote sites, tight programmes

Supervisor day rates, visa, insurance and accommodation terms: to confirm.

Responsibilities

Who does what on site

Hạng mụcYou or your contractorGGSteel
Foundations and anchor boltsYesAnchor bolt plan and templates
Site safety plan, permitsYes (unless full team)Method statements
Cranes and accessYes (unless full team)Lifting weights and pick points
Unloading and laydownYesDelivery sequence by zone
Erection, bolting, plumbingYour erector, or oursSupervision and sign-off
Missing or wrong partsReport with photosReplacement or site fix
Bu lông neo

The most common delay, and how to avoid it

Anchor bolts are set by the foundation contractor, often weeks before the steel arrives. If they are out of tolerance, the first column will not fit.

Kiểm traAISC 303 (USA)Ghi chú
Bolts within one group, centre to centre±3 mm (1/8 in)Most critical for base plate fit
Group centre to its intended location±6 mm (1/4 in)Measured from the established column line
Projection above concretePer contract documentsToo short and nuts cannot engage

AISC 303 values. GB 50205 and EN 1090-2 set their own limits; ACI 117 is wider than AISC, a known conflict noted by ASCC Position Statement 14.

Survey before shipping. Send us a survey of the anchor bolts before the last steel ships. We adjust base plates in the shop if needed.
Use templates. Our anchor bolt templates hold bolts in position during the pour.
If bolts are out. Options include enlarged or slotted holes with plate washers, or new post-installed anchors. Your engineer must approve each fix.
Before the steel arrives

Site checklist

Erection sequence

A typical single-storey frame

01

Survey

Anchor bolts and levels checked.

02

First bay

Columns and rafters of a braced bay erected and plumbed.

03

Frames

Following frames tied back to the braced bay.

04

Bracing

Roof and wall bracing installed and tensioned.

05

Phụ

Purlins, girts and sag rods.

06

Envelope

Roof and wall sheets, flashings.

Pace depends on crane count, crew size and weather. Typical single-storey warehouse: 150–300 t per week per crane team.

Missing or wrong parts

What happens when something does not fit

01

Report

Photo with the member mark and the problem.

02

Diagnose

Our engineer checks the drawing, the trace log and the packing list.

03

Decide

Site fix, shop remake, or part from spare stock.

04

Supply

Our error: at our cost. Air freight policy: to confirm.

Spares ship with the steel: a percentage of bolts and small fittings, to confirm, so most small losses are fixed on the day.
Overseas erection

Where we have worked on site

Lao International Tobacco Plant

185,550 m², 12,600 t, erected by GGSteel.
Laos

Naypyidaw Stadiums 1–3

96,000 m², 14,340 t, erected by GGSteel.
Myanmar

Magelang Bottled Water Plant

78,757 m², 2,600 t, site construction by GGSteel.
Indonesia
Câu hỏi thường gặp

Erection questions

Not answered here? Hỏi kỹ sư.

Which languages do your supervisors speak?

Mandarin and English; other languages through local interpreters.

The main contractor, unless we take the full erection scope.

Yes, for simple portal frames with an experienced crew. For box columns, trusses and composite frames we recommend a supervisor.

Yes, lifting plans and temporary works for our members. Crane selection stays with the crane contractor.

Liên quan

Services and pages that connect to this one

Packing & Shipping

Service

Fabrication to Drawings

Service

Become an erection partner

Công ty

Markets we serve

Công ty
On site

Tell us about your site and crew

We suggest the support level with the steel quote.