Beranda / Produk / Commercial & High-rise

Steel Buildings

Steel and composite frames for towers, podiums and public buildings

Tower steel is thick, heavy and full of interfaces. Plates of 60 mm and more need through-thickness grades and preheat. Columns carry rebar and studs. Every splice level follows the concrete pour. These are the points we check before shop drawings.

241 m

Tallest tower, Zengcheng C1

18.472 t

CGN HQ steel, 3 towers

Q420GJC

Thick-plate grade used

6,500 t

Xintang railway station

Fit

When a steel or composite frame makes sense

A good fit when

Think twice when

Frame systems

SRC, CFT or bare steel

SystemPenggunaan tipikalStrengthWatch out for
SRC (steel-reinforced concrete) columnsTower perimeter and coreStiffness, fire cover from concreteRebar holes and stud clashes
CFT (concrete-filled steel tube)Podium and mega columnsSmall section, no formworkFilling quality, vent and pour holes
Bare steel with composite floorsOffices, hospitals, schoolsFast, long spansFire protection, floor vibration
Outriggers and belt trussesSuper-tall towersControls driftHeavy nodes, erection sequence
Kasau atap bentang panjangStations, halls, atriaColumn-free spaceTransport length, trial assembly
Thick plate

Lamellar tearing, Z-grades and preheat

Thick plates loaded through their thickness by large welds can tear in layers. It is prevented at the material order, not at inspection.

RiskControlStandar
Lamellar tearing at T-jointsThrough-thickness grade Z15, Z25 or Z35 ordered for plates loaded through thicknessGB/T 5313, EN 10164
Laminations in the plateUltrasonic testing of plate before cuttingGB/T 2970, EN 10160
Cold cracking of thick weldsPreheat and interpass temperature by thickness and carbon equivalentGB 50661, AWS D1.1, EN 1011-2
Distortion of box columnsWeld sequence, restraint, post-weld correctionOur procedure qualification
Hidden defects in full-penetration welds100% UT for grade 1 weldsGB 50205, GB/T 11345

Plate thickness limits we fabricate: to confirm in writing.

Antarmuka

Steel, rebar and concrete in one model

Most rework on composite towers comes from interfaces drawn by different teams at different revisions.

Multi-storey steel frame building under construction
From our engineers

Three tower problems solved in the shop

Column shortening. Steel and concrete columns shorten differently under load and creep. Your engineer sets the compensation; we add it to each column tier length.
Verticality. Columns are surveyed every tier. The erection manual sets shim and splice adjustment limits.
Piece weight. Tower crane capacity at the working radius sets column piece weight and splice levels, so the crane study comes before shop drawings.
Pemasangan

How a steel tower goes up

01

Crane study

Capacity sets piece weight and splices.

02

Column tiers

Two or three floors per tier.

03

Beams and bracing

Frame closed and plumbed.

04

Dek lantai

Deck laid, studs welded.

05

Concrete

Pours follow steel by agreed floors.

06

Survey

Verticality corrected each tier.

High-rise projects

Towers and public buildings

CGN Engineering Headquarters

18,472 t · SRC box columns
Shenzhen

Zengcheng New World Complex

241 m · 7.000 t Q420GJC
Guangzhou

Rumah Sakit Pusat Longgang

Healthcare
Shenzhen
FAQ

High-rise steel questions

Not answered here? Tanya insinyur.

Do you design the tower structure?

For towers, the design institute or your engineer of record usually designs it. We do connection design, shop drawings, fabrication, and erection on Chinese projects.

When a plate is loaded through its thickness by large welds, typically column flanges at beam joints. Your engineer names the grade; we flag joints where it appears missing.

Up to about 40 t per piece; the site crane usually sets the real limit.

Column and beam studs are shop-welded where they do not obstruct erection. Deck studs are site-welded through the deck.

Yes, to EN 1090-2 or AISC 303 execution requirements named in your specification. We do not hold EN 1090 certification.

Langkah selanjutnya

Related pages

Welded Box Columns

Produk

Lantai Rangka

Produk

Complex Steel Nodes

Produk

Engineering & Detailing

Service
High-rise frame

Send the column and beam schedule

We check plate grades, SRC interfaces, splice levels and piece weights with the quote.