Rebar drawings at the same revision as steel. Holes cannot be moved after the box is closed.
Splice levels set with the concrete contractor. Pour heights and splice heights must agree.
Fire strategy for exposed steel. Concrete cover protects SRC; the exposed parts still need a system.
Tower crane capacity. It sets the maximum piece weight and so the splice positions.