Steel detailing and connection design, with responsibility written down

Most disputes on steel projects start with one question: who was responsible for that detail? This page sets out what we design, what we only draw, and what happens when a drawing is wrong.

Since 2014

Group design company

Tekla

Detailing model

4 code families

GB, AISC, EN, AS/NZS

2 days

RFI list from receipt

Service levels

Three levels, three different responsibilities

NivelWhat we doDesign responsibilityTypical client
Scheme designStructural system, member sizes, tonnage estimateGGSteel for the scheme; a local engineer usually checks and stampsOwners with a brief
Connection design (delegated)Design of connections from member forces on your drawingsYour engineer for members; our engineer for connectionsContractors with IFC drawings
Shop drawings onlyModel and drawings from fully detailed designYour engineer of recordContractors with complete details
Local stamping: most countries require a locally registered engineer to sign structural design. We provide calculations and drawings in the format your engineer needs; we do not claim a stamp we cannot give.
Inputs

What we need before detailing starts

Connection design

Who designs the connections, by code

CodeOptionsWhat we provide
AISC 303 (USA)Option 1: shown in full by the EOR. Option 2: fabricator completes simple connections from tables. Option 3: delegated to the fabricator’s licensed engineerOptions 2 and 3, with calculations for your EOR’s review
EN 1993-1-8 (Europe)Joints designed by the designer or delegated with execution specificationJoint calculations per EN 1993-1-8
GB 50017 (China)Usually the design institute shows main joints; fabricator completes detailsJoint calculations and node drawings
AS 4100 (Australia)Design or delegated design per specificationCalculations to AS 4100

Option numbering per AISC 303. Your contract decides which option applies.

Approval cycle

How drawings move between us and your engineer

01

RFI list

Missing data and conflicts listed within 2 working days.

02

Model

Frame, connections and openings modelled.

03

Submission

Drawings issued in batches by zone.

04

Review

Your engineer returns each sheet coded A, B, C or D.

05

Revision

B and C comments closed out and re-issued.

06

Release

Only A and B sheets go to the workshop.

CodeMeaningCan fabrication start?
AAprobadoYes
BApproved as notedYes, with comments applied
CRevise and resubmitNo
DRejectedNo

Typical review turnaround we plan for: 5–10 working days per batch; typical rounds: 2. Your specification may set its own codes.

When a drawing is wrong

Who pays for detailing errors

CauseWho is responsibleWhat happens
Our detail does not match the approved designGGSteelWe fix or remake the member at our cost
Dimension or hole error in our shop drawingGGSteelSame, even if your engineer approved the sheet
Design drawing was wrong or changedYour engineerChange logged with cost and time before we proceed
Site conditions differ from drawingsBy contractSite fix proposed and priced
Approval does not move responsibility. Under AISC 303, approval confirms that we read the design correctly; we remain responsible for the dimensions and details in our shop drawings.
Entregables

What you receive, and in which format

DeliverableFormatoDetail level
Detailing modelTekla; IFC exportLOD 400 (fabrication) for steel; LOD 300 is design only
GA and marking plansPDF, DWGEvery member mark located
Assembly and part drawingsPDF, DWGEvery hole, weld and cut
CNC filesDSTV / NC1For our machines; available on request
Cálculos de conexionesPDFWhere connection design is in scope
BOM, bolt list, paint areasExcelBy zone and member
RFI and revision logExcelEvery question and change, dated
From our engineers

Clashes we look for before you see the drawings

Rebar through steel. In SRC columns, rebar holes, couplers and studs are placed from a combined model. CGN HQ is a project of this type.
Services through beams. Duct and pipe openings in webs are agreed before detailing, with reinforcement where needed.
Splices and cranes. Splice positions follow crane capacity and transport length, not only member forces.
Preguntas frecuentes

Preguntas de detallado

Not answered here? Pregunte a un ingeniero.

Can you work from Revit or Rhino models?

Yes. We import via IFC into Tekla and report anything that does not translate.

About 2–4 weeks for 1,000–3,000 t, issued by zone so fabrication can start earlier.

Yes, for connections and scheme design. Your local engineer of record keeps responsibility for the structure.

Yes.

Numbers to confirm.

Relacionado

Services and pages that connect to this one

Fabrication to Drawings

Service

Diseño vs planos de taller

Guide

Complex Steel Nodes

Producto

CGN HQ case study

Proyecto
Drawing review

Send drawings, get an RFI list in 2 working days

A free review before you commit to an order.