1. Home
  2. Projects
  3. Shenshan 750 kt Grain Reserve
Case study · Grain storage
Main contractor: CSCEC 5th Bureau (north zone)Tandem lift, 2 × 600 t cranesQ355B

Shenshan 750 kt Grain Reserve: A 47 m Trestle Lifted 50 m High

Steel conveyor trestles and roof steel for a 750,000 t national grain reserve behind Xiaomo Port in the Shenzhen-Shanwei Special Cooperation Zone. The Lot 3 trestle, 47 m long, was lifted in one piece by two 600 t mobile cranes.

750,000 tGrain storage capacity
47 mTrestle span
50 mTrestle height above grade
223,000 m²Gross floor area
01Project facts

Storage, transfer and processing on one port site

The Shenshan grain reserve combines strategic storage, port transfer and emergency processing on a 350,000 m² site behind Xiaomo Port. It uses shallow-round silos, vertical silos and low-temperature warehouse blocks, linked by enclosed conveyor trestles that carry grain between the berth, the silos and the processing buildings.

Guiguan fabricated steel trestles, trestle support towers and roof steel for the storage buildings. The highlight was Lot 3: a 47 m trestle span set 50 m above grade between two silo groups.

Silo and trestle zone during construction
ItemDetail
OwnerShenshan grain reserve authority (state grain reserve project)
Main contractorChina State Construction 5th Engineering Division (north zone)
LocationBehind Xiaomo Port, Shenzhen-Shanwei Special Cooperation Zone, Guangdong
Building typeGrain silos, warehouses, conveyor trestles, processing plant
Site / GFA350,000 m² site · 223,000 m² GFA
Capacity750,000 t of grain
Trestle47 m span, 50 m elevation, enclosed box-truss gallery
Structural steelapprox. 3,800 t across trestles, towers and roofs (estimated)
Steel gradesQ355B; Q355C for exposed coastal members
Our scopeDetailing, fabrication, trial assembly, coating, delivery, lift engineering support
ProgramStart December 2022 · operation planned end 2025

Tonnage and member data from fabrication records; areas and dates from the owner and main contractor.

02The challenge

A long, light, high span in a coastal wind zone

Conveyor trestles are long and slender. At 50 m above grade on the South China coast, wind and lift stability governed more than grain load.

47 m span at 50 m

The trestle bridged two silo groups with no intermediate support. It had to be stiff enough for conveyor alignment and light enough for a two-crane lift.

Typhoon exposure

Coastal Guangdong design wind pressures, with the gallery cladding adding sail area to the truss.

Live silo interfaces

Trestle ends sat on silo-top structures and towers with tight bearing tolerances and thermal movement.

Lift stability

A long box truss must not twist or overstress during a tandem lift. Lifting points and temporary bracing were part of the design.

Marine corrosion

Salt-laden air near the port called for a heavy-duty coating system and sealed box members.

Dust and fire

Grain dust requires smooth, cleanable steel surfaces and explosion-relief detailing in galleries.

03Engineering solution

A box truss built as one piece, lifted as one piece

The trestle is a rectangular box truss: two vertical Warren trusses for the sides, with top and bottom chord bracing forming a closed tube for torsional stiffness. Chords are welded H-sections; diagonals and verticals are H and tube sections. The conveyor runs on the bottom deck and the gallery is clad on a light frame.

We fabricated the trestle in transportable segments and trial-assembled the full 47 m length in the yard, surveying camber and diagonals before match-marking. On site it was bolted together at ground level, then lifted by two 600 t mobile cranes. Lifting lugs were designed at the panel points so each crane took its share without local buckling. One end bears on a fixed bearing, the other on a sliding bearing to release thermal movement.

Long-span truss in shop trial assembly
Member / detailSection & gradeDetailing note
Trestle chordsWelded H 400×400 to 500×400, Q355BBolted splices at segment joints, match-marked
Diagonals / verticalsH 250–350 and tube Φ219–299, Q355BGusset connections, seal-welded tubes
Plan bracingAngles and tubes, Q355BClosed tube action for torsion during lift
Support towersBox columns 600×600, Q355CFour-leg braced towers, HSFG bolted
BearingsFixed + sliding steel bearingsSliding end releases thermal movement
Lifting lugsPlate lugs t = 40–50 mm, Q355CAt panel points, 100% UT, removed after lift
Fabrication & QC, Guangdong base
04Fabrication & QC

Full-length trial assembly before shipping

The full 47 m trestle was assembled in the yard and surveyed for length, camber, diagonal difference and bearing positions. Lifting lugs and their welds received 100% UT and MT and were load-checked against the lift plan. Coating used a C5 marine system: Sa2.5 blasting, zinc-rich epoxy primer, epoxy intermediate and polyurethane top coat, about 240 µm total DFT.

  • Full trial assembly of the 47 m span in the shop yard
  • Camber and diagonal checks within L/1000
  • 100% UT on CJP welds and all lifting lug welds
  • C5 marine coating, DFT recorded per piece
  • Lift plan reviewed with the crane contractor
05Delivery & erection

From yard assembly to a two-crane lift

The lift took a single day. The preparation took weeks.

  1. 01

    Detailing and lift design

    Tekla model of trestle and towers; lift points, rigging and temporary bracing checked with the crane contractor.

  2. 02

    Shop fabrication

    Chords, diagonals and towers fabricated in Q355B; lifting lugs welded and tested.

  3. 03

    Trial assembly

    Full 47 m span assembled, surveyed and match-marked, then split for transport.

  4. 04

    Site assembly

    Segments bolted together on a ground jig; conveyor deck and bracing installed before lifting.

  5. 05

    Tandem lift

    Two 600 t mobile cranes raised the trestle about 50 m and set it on fixed and sliding bearings.

  6. 06

    Fit-out

    Gallery cladding and conveyor installed; final survey of bearing and alignment.

06Results

One lift, no site modification

47 mSpan lifted in one piece
50 mLift height
2Cranes, 600 t each
750 ktGrain reserve capacity

Because the span was trial-assembled and surveyed in the yard, site assembly was a bolting exercise and the trestle seated on its bearings without modification. Lifting at ground-assembled weight with conveyor deck in place cut high-level work to bearing fixing and cladding.

For port, mining and agri-bulk owners overseas, the same method works for conveyor galleries and transfer towers shipped from South China. See grain and silo structures and coating systems.

07Related

Systems and members used on this project

Each page lists spans, grades and processing limits. See all reference projects.

08FAQ

Questions about this project

Planning a similar structure? Send drawings and our engineers reply within 24 hours.

What did Guiguan supply for the Shenshan grain reserve?

Steel conveyor trestles, trestle support towers and roof steel for storage buildings, including the 47 m Lot 3 trestle. We provided trial assembly, coating and lift engineering support to the main contractor.

It was assembled at ground level from trial-assembled segments, then lifted about 50 m in one piece by two 600 t mobile cranes onto fixed and sliding bearings.

Typically a C5 system: Sa2.5 blast, zinc-rich epoxy primer, epoxy intermediate and polyurethane top coat, around 240 µm. Hot-dip galvanizing is an option for secondary steel.

Yes. Trusses are trial-assembled to 90 m, split into segments up to 24 m and 60 t for break-bulk, and match-marked for site assembly.

Both. We fabricate to your design, or our engineers develop connection design and lift checks to AISC 360, EN 1993 or AS 4100 for your engineer’s approval.

Send your drawings. Get a 24-hour BOM and FOB price.

DWG, IFC, Tekla or PDF. Engineering review by our Tekla team, from 50 t or 2,000 m².